Published on August 1, 2026 10 min read EnerPHit · Minergie-P Retrofit IDC · Project strategy Updated June 2026

Retrofitting in Geneva: IDC, standards and strategy

In Geneva, the IDC now triggers legal obligations for building owners — and a retrofit is first and foremost a matter of strategic choices. This dossier sets out the framework: IDC thresholds, the EnerPHit and Minergie-P Rénovation standards, project approach and phasing. Implementation — envelope, airtightness, systems — is detailed in the practical dossier.

In this dossier

Why retrofit to this level?

A large share of the Swiss building stock was built before the first meaningful thermal requirements of the 1980s, without significant insulation. The order of magnitude can be read off the Geneva regulations: above 125 kWh/m²·an (450 MJ/m²·an) of heating expenditure indexThreshold set by the Geneva REn (rsGE L 2 30.01, art. 14): above 125 kWh/m²·an (450 MJ/m²·an), an energy audit and improvement measures are required.République et canton de Genève — Règlement d'application de la loi sur l'énergie (REn), rsGE L 2 30.01, art. 14 et 14Baccessed 2026-08-20, an energy audit becomes mandatory — an unrenovated building from that era frequently crosses that threshold. Switzerland has set itself the target of carbon neutrality by 2050Confirmed by the SFOE: net-zero CO₂ emissions by 2050, with building stock consumption cut from around 90 TWh to 65 TWh.Office fédéral de l'énergie (OFEN/BFE) — Buildings — Energy efficiencyaccessed 2026-08-20: this means deeply retrofitting most of this building stock, not just replacing boilers.

A superficial retrofit (replacing windows, a more efficient gas boiler) brings only a marginal improvement. Only a coordinated envelope + systems retrofit can divide heating consumption by a factor of roughly 5 — from the 125 kWh/m²·an of the Geneva audit thresholdFactor derived from two sourced values: the Geneva audit threshold of 125 kWh/m²·an (REn art. 14) and the EnerPHit target of ≤ 25 kWh/(m²a) (PHI criteria) — a ratio of about 5.Passivhaus Institut, Darmstadt — Criteria for the Passive House, EnerPHit and PHI Low Energy Building Standards2022 · accessed 2026-08-20 down to the ≤ 25 kWh/m²·an targeted by EnerPHit — and achieve lasting thermal comfort.

Retrofitting to the passive standard does not mean sticking insulation everywhere. It is a comprehensive design approach that treats the existing envelope as a coherent system — with its own constraints and opportunities.
≈ 40 %
of Switzerland's final energy consumption is accounted for by buildingsConfirmed by the SFOE: buildings consume about 90 TWh, i.e. some 40 % of Swiss final energy demand, with a 65 TWh target for 2050.Office fédéral de l'énergie (OFEN/BFE) — Buildings — Energy efficiencyaccessed 2026-08-20
≤ 25
kWh/m²·an: EnerPHit threshold (net heating demand after passive retrofit)Confirmed: PHI criteria, EnerPHit heating demand ≤ 25 kWh/(m²a) in a cool-temperate climate, against ≤ 15 kWh/(m²a) for a new Passive House.Passivhaus Institut, Darmstadt — Criteria for the Passive House, EnerPHit and PHI Low Energy Building Standards2022 · accessed 2026-08-20
÷ 5
order of magnitude of the reduction: from the Geneva audit threshold to EnerPHit level
≈ 1/3
of Switzerland's CO₂ emissions come from buildingsSFOE figure: buildings account for about one third of Swiss CO₂ emissions and close to 40 % of final energy consumption.Office fédéral de l'énergie (OFEN/BFE) — Buildings — Energy efficiencyaccessed 2026-08-20
Subsidies available in French-speaking Switzerland The Programme Bâtiments (Confederation + cantons) subsidizes retrofits that reach high performance levels. In Geneva, the 2026 scheme carries CHF 80 million and brings together the DepartmentCanton of Geneva, 2 February 2026: run by the Department of Economy and Employment, the SIG and the Programme Bâtiments; the AMO subsidy expires and is discontinued in 2026.République et canton de Genève — Subventions énergétiques 2026 : 80 millions de francs pour accélérer la rénovation du parc bâti genevois2026-02-02 · accessed 2026-08-20 of Economy and Employment, the Services industriels de Genève and the Confederation's Programme Bâtiments; HPE (high energy performance) and THPE (very high energy performance) retrofits attract specific grants, and Minergie®-certified works benefit from a bonus. The owner's-representative (AMO) subsidy was discontinued in 2026. Rates are revised annually and should be checked before any application: leprogrammebatiments.ch or through the SIG-éco21 partners.Official Programme Bâtiments domains: leprogrammebatiments.ch (FR), dasgebaeudeprogramm.ch (DE), ilprogrammaedifici.ch (IT).Confédération suisse et cantons — Le Programme Bâtimentsaccessed 2026-08-20

The IDC: what Geneva law requires of building owners

In Geneva, owners of heated buildings declare their building's IDC — Indice de Dépense de Chaleur (heating expenditure index) to the OCEN each year: the actual heating and domestic hot water consumption, measured at the meters and expressed per unit of reference energy floor area. It is not a theoretical calculation — it is the building's real energy bill. Not to be confused with individual heating-cost accounting, which applies to buildings with at least 5 heat off-takers (REn art. 14B)Two distinct regimes in the Geneva REn: the IDC (art. 14) applies to owners of heated buildings; individual heating-cost accounting (art. 14B) applies from 5 off-takers.République et canton de Genève — Règlement d'application de la loi sur l'énergie (REn), rsGE L 2 30.01, art. 14 et 14Baccessed 2026-08-20: that is a separate rule, unrelated to the scope of the IDC.

This index is no longer just a monitoring tool: it triggers legal obligations for building owners.

> 125
kWh/m²·an (450 MJ/m²·an): above this IDC threshold, an energy audit of the building is mandatoryConfirmed by the OCEN: above 125 kWh/m²·an (450 MJ/m²·an), an energy audit and optimisation measures are required (REn art. 14; LEn art. 15C).République et canton de Genève (OCEN) — Que faire selon le résultat IDC de votre immeubleaccessed 2026-08-20
> 180
kWh/m²·an (650 MJ/m²·an): the significant-exceedance threshold, above which remediation works are orderedGeneva REn, art. 14: significant exceedance set at 800 MJ/m²·an until 31.12.2026, 650 MJ/m²·an from 01.01.2027 to 31.12.2030, 550 MJ/m²·an from 01.01.2031.République et canton de Genève — Règlement d'application de la loi sur l'énergie (REn), rsGE L 2 30.01, art. 14 et 14Baccessed 2026-08-20, from 2027 (800 MJ/m²·an until end of 2026, 550 MJ/m²·an from 2031)
36 months
to carry out the works ordered after a significant exceedance; 12 monthsGeneva REn, art. 14: works ordered after a significant exceedance must be carried out within 36 months; improvement measures after a simple exceedance within 12 months.République et canton de Genève — Règlement d'application de la loi sur l'énergie (REn), rsGE L 2 30.01, art. 14 et 14Baccessed 2026-08-20 for the improvement measures after a simple exceedance
1 kWh = 3,6 MJ
the IDC is often expressed in MJ/m²·an: 125 kWh ≈ 450 MJ, 180 kWh ≈ 650 MJ
In practical terms, for an owner or a property management firm An unrenovated building from the 1960s–1980s frequently exceeds these thresholds. Waiting for the letter from the OCEN means being subject to its timetable; anticipating the audit means choosing your own strategy — which works, in what order, with which subsidies. This is precisely the difference between a retrofit imposed piecemeal and a planned retrofit that adds value to the building.

EnerPHit and Minergie‑P Rénovation

Two main standards define "passive retrofit" in French-speaking Switzerland: EnerPHit (Passivhaus Institut, Darmstadt) and Minergie-P Rénovation. Their requirements differ in logic, but their shared goal is to reach a performance level close to new passive construction, while accounting for the constraints of the existing building stock.

EnerPHit
Heating demand
≤ 25 kWh/m²·an (PHPP)
or a component-based approach (U-values)

Airtightness
n₅₀ ≤ 1,0 h⁻¹
(vs 0,6 for new Passivhaus)

Key feature
Dual certification path: either the overall energy balancePHI criteria: EnerPHit compliance is shown either by the component method (table 2) or by the energy demand method (table 3) — only one of the two need be met.Passivhaus Institut, Darmstadt — Criteria for the Passive House, EnerPHit and PHI Low Energy Building Standards2022 · accessed 2026-08-20, or compliance with target U-values per component (a more flexible approach for phased retrofits).
Minergie-P for retrofits
Heating demand
≤ 90 % of MoPEC 2025 (cantonal model energy regulations) limit valuesMinergie regulation 2026.1, sec. 6.1: retrofit ≤ 90 % of the Qh,li MoPEC 2025 limit values per SIA 380/1:2016; ≤ 70 % for new build.Minergie Suisse — Règlement des labels MINERGIE®/MINERGIE-P®/MINERGIE-A®, version 2026.12026 · accessed 2026-08-20 for retrofits (SIA 380/1:2016)
(vs ≤ 70% for new Minergie-P — regulation 2026.1)

Airtightness
qE50 ≤ 1,6 m³/(h·m²) for retrofits

Key feature
Official recognition by the Swiss cantons. Minergie-P applies to new build and retrofit alike: regulation 2026.1 defines no separate "Minergie-P Rénovation" labelChecked against Minergie regulation 2026.1: Minergie-P covers new build and retrofit under a single procedure; neither module certification nor a dedicated procedure for protected buildings appears in it.Minergie Suisse — Règlement des labels MINERGIE®/MINERGIE-P®/MINERGIE-A®, version 2026.12026 · accessed 2026-08-20, no module-by-module certification and no dedicated procedure for protected buildings — those instruments belong to the Minergie Rénovation products.

Take care when comparing the numerical thresholds: the reference energy floor area (SRE) is not calculated the same way between Passivhaus (PHPP reference floor area, PHI Darmstadt) and Minergie® (SRE per SIA 416). The two requirements are not even of the same kind — EnerPHit sets an absolute value (≤ 25 kWh/m²·an), Minergie-P a percentageNo Minergie document sets an absolute "≤ 30" value: regulation 2026.1 expresses retrofit as a % of MoPEC 2025 (≤ 90 %), with a 15 kWh/m²·an floor.Minergie Suisse — Règlement des labels MINERGIE®/MINERGIE-P®/MINERGIE-A®, version 2026.12026 · accessed 2026-08-20 of the MoPEC 2025 limit values — so that a direct comparison of the figures would make no sense.

EnerPHit's component-based approach: welcome flexibility When it is not possible to reach the overall threshold of 25 kWh/m²·an (compact building, heritage constraints, phasing over several years), EnerPHit allows component-based certification: each renovated envelope element must meet specific target U-values. This approach allows for progressive certification, component by component: the PHI criteria set no maximum periodThe PHI criteria mention no maximum time limit: the EnerPHit Retrofit Plan allows pre-certification, then a certificate application after the final step.Passivhaus Institut, Darmstadt — Criteria for the Passive House, EnerPHit and PHI Low Energy Building Standards2022 · accessed 2026-08-20 — an EnerPHit Retrofit Plan can be pre-certified, and the certificate applied for after the final step.
Criterion Passivhaus New Build EnerPHit Retrofit Minergie-P New Build Minergie-P Retrofit
Heating demand ≤ 15 kWh/m²·an ≤ 25 kWh/m²·an ≤ 70 % MoPEC 2025 ≤ 90 % MoPEC 2025
Airtightness * n₅₀ ≤ 0,6 h⁻¹ n₅₀ ≤ 1,0 h⁻¹ qE50 ≤ 0,8 m³/(h·m²) qE50 ≤ 1,6 m³/(h·m²)
Heating capacity ≤ 10 W/m² ≤ 10 W/m²
Phased certification ✓ Components
Calculation tool PHPP PHPP SIA 380/1 SIA 380/1
Protected buildings ⚠ Case by case

* Passivhaus/EnerPHit measure n₅₀ (air changes per volume), Minergie® measures qE50 (leakage flow rate per envelope surface area, EN ISO 9972:2015 + SIA 180:2014Edition in force for air permeability measurement: ISO 9972:2015, complemented by SIA 180:2014 for Swiss application.Minergie Suisse — Règlement des labels MINERGIE®/MINERGIE-P®/MINERGIE-A®, version 2026.12026 · accessed 2026-08-20) — the two quantities are not directly comparable. Minergie® values according to regulation 2026.1 (fossil fuels prohibited, absolute minimum of 15 kWh/m²·an)Minergie regulation 2026.1, sec. 8.1: fossil fuels not allowed for heat generation, with narrow exceptions (peak load ≤ 10 % above 80 kW; district heating ≤ 50 % fossil).Minergie Suisse — Règlement des labels MINERGIE®/MINERGIE-P®/MINERGIE-A®, version 2026.12026 · accessed 2026-08-20.

Implementation, component by component Envelope strategy (façades, roof, windows, thermal bridges), airtightness plane, ventilation and heating: the technical detail is covered in a dedicated dossier — Passive retrofit in practice →

How to run a passive retrofit project

A passive retrofit cannot be improvised after the fact: decisions made at the design stage determine 80% of the result. Here is the typical sequence of a well-run project.

Step 1 — Diagnosis
Energy and technical baseline survey
A full thermal audit precedes every decision: survey of existing U-values, measurement of the building's air permeability, infrared imaging in cold weather and mapping of thermal bridges — these measurements are carried out by a specialist firm or a testing contractor. Add to that the identification of any heritage constraints. This diagnosis guides everything: without it, it is impossible to define objectives or cost the works.
Step 2 — Preliminary design
Defining the envelope + systems strategy
Choice of target standard (EnerPHit, Minergie-P, or an intermediate level) and construction system variants per component. Whether the targets are met is checked by a preliminary thermal calculation — PHPP for EnerPHit, SIA 380/1 for Minergie — carried out by the design team or a specialist consultancy. Cost assessment per variant and identification of subsidies, which must be applied for before works begin.
Step 3 — Detailed design
Detailed design of construction junctions
Drawings of all critical construction junctions (façade/slab junction, window/ITE junction, wall base), with the building physics consultancy quantifying the remaining thermal bridges (Ψ). Definition of the airtightness plane with continuity details at every critical point. Sizing of the ventilation system and heat generation. This is where it is won or lost: a junction that is not drawn is a junction improvised on site.
Step 4 — Construction
Quality control and intermediate testing
Site supervision with particular attention to the interfaces between trades (masonry/joinery/airtightness). Before the build-ups are closed, a testing contractor runs an intermediate airtightness test: at that stage a leak can be located and sealed cheaply, whereas once the finishes are on it becomes practically unreachable — which is precisely why the timing matters. Sign-off of construction junctions before they are covered. Training of tradespeople on airtightness requirements (the weak link is often a lack of awareness on site).
Step 5 — Handover and certification
Final airtightness test, as-built calculation, certification file
A final airtightness test (n₅₀ ≤ 1,0 h⁻¹) is run by the testing contractor, and the PHPP or SIA 380/1 calculation is updated with actual values by the thermal consultancy. The certification file is then assessed by the certifying body — the Passivhaus Institut for EnerPHit, Minergie Suisse for Minergie-P — and not by the design team. Consumption measurements over the first heating season allow the result to be verified.
Phased retrofit: planning for coherence from the outset Many retrofits are carried out in several phases (windows one year, façade three years later, roof afterwards). This is often a financial necessity. But without an overall plan, each phase can compromise the next: windows replaced before the ITE will end up in the wrong position and create thermal bridges. The golden rule: design the complete project from the outset, even if execution is phased.

What building owners ask

How much does a retrofit to the passive standard cost?

Costs vary enormously depending on the building's initial condition, its geometry, the presence of structural thermal bridges, and the choice of materials: there is no public cost database that would allow a reliable price per m² to be quoted for a retrofit to passive level, and any serious costing requires a quotation on the actual building. What is public and quantified, by contrast, is the support. In Geneva, measure M-13 "HPE retrofit, CECB® variant" pays 390 CHF/m²GEnergie rate, measure M-13 "HPE retrofit, CECB® variant": 390 CHF/m² for single-family housing, 210 CHF/m² collective, 150 CHF/m² other uses. Revised annually.GEnergie / canton de Genève — HPE — Rénovation variante CECB®, mesure M-13accessed 2026-08-20 of heated floor area for single-family housing and 210 CHF/m² for collective housing; the 2026 cantonal budget amounts to CHF 80 millionCanton of Geneva announcement of 2 February 2026: CHF 80 million in energy subsidies for 2026, CHF 10 million more than in 2025.République et canton de Genève — Subventions énergétiques 2026 : 80 millions de francs pour accélérer la rénovation du parc bâti genevois2026-02-02 · accessed 2026-08-20. Since the rates are revised annually, they should be checked before any application. The return on investment is also measured in comfort, property value, and protection against energy price volatility.

Can a retrofit be done in stages without doing everything at once?

Yes — it is even the most common situation. The key is to design the project as a whole before starting the first phase, to ensure that each intervention is consistent with those that follow. The rule: start with the roof (the most cost-effective energy-wise), then the façades, then the windows (taking into account their final position within the insulated wall), then the systems. Never replace the windows before deciding on the façade insulation system.

What is the difference between a "Minergie" retrofit and an "EnerPHit" retrofit?

Both standards target a similar level of performance and allow a component-based approach. Minergie-P is more widely recognized in the Swiss context, with a well-established cantonal procedure and better integration into subsidy applications. EnerPHit is the Passivhaus Institut's international standard: it is recognized outside Switzerland and its PHPP methodology is very precise. In practice, building owners in Geneva or Vaud will often choose Minergie-P Rénovation for its administrative ease, while EnerPHit will be preferred for projects with strong technical stakes or an exemplary role.

Sources and references (21)

Every figure and every claim in this dossier links back to its source. Hover or tap a footnote marker to see it.

  1. République et canton de Genève — Règlement d'application de la loi sur l'énergie (REn), rsGE L 2 30.01, art. 14 et 14B (accessed 2026-08-20)
    Threshold set by the Geneva REn (rsGE L 2 30.01, art. 14): above 125 kWh/m²·an (450 MJ/m²·an), an energy audit and improvement measures are required.
  2. Office fédéral de l'énergie (OFEN/BFE) — Buildings — Energy efficiency (accessed 2026-08-20)
    Confirmed by the SFOE: net-zero CO₂ emissions by 2050, with building stock consumption cut from around 90 TWh to 65 TWh.
  3. Passivhaus Institut, Darmstadt — Criteria for the Passive House, EnerPHit and PHI Low Energy Building Standards (2022 · accessed 2026-08-20)
    Factor derived from two sourced values: the Geneva audit threshold of 125 kWh/m²·an (REn art. 14) and the EnerPHit target of ≤ 25 kWh/(m²a) (PHI criteria) — a ratio of about 5.
  4. Office fédéral de l'énergie (OFEN/BFE) — Buildings — Energy efficiency (accessed 2026-08-20)
    Confirmed by the SFOE: buildings consume about 90 TWh, i.e. some 40 % of Swiss final energy demand, with a 65 TWh target for 2050.
  5. Passivhaus Institut, Darmstadt — Criteria for the Passive House, EnerPHit and PHI Low Energy Building Standards (2022 · accessed 2026-08-20)
    Confirmed: PHI criteria, EnerPHit heating demand ≤ 25 kWh/(m²a) in a cool-temperate climate, against ≤ 15 kWh/(m²a) for a new Passive House.
  6. Office fédéral de l'énergie (OFEN/BFE) — Buildings — Energy efficiency (accessed 2026-08-20)
    SFOE figure: buildings account for about one third of Swiss CO₂ emissions and close to 40 % of final energy consumption.
  7. République et canton de Genève — Subventions énergétiques 2026 : 80 millions de francs pour accélérer la rénovation du parc bâti genevois (2026-02-02 · accessed 2026-08-20)
    Canton of Geneva, 2 February 2026: run by the Department of Economy and Employment, the SIG and the Programme Bâtiments; the AMO subsidy expires and is discontinued in 2026.
  8. Confédération suisse et cantons — Le Programme Bâtiments (accessed 2026-08-20)
    Official Programme Bâtiments domains: leprogrammebatiments.ch (FR), dasgebaeudeprogramm.ch (DE), ilprogrammaedifici.ch (IT).
  9. République et canton de Genève — Règlement d'application de la loi sur l'énergie (REn), rsGE L 2 30.01, art. 14 et 14B (accessed 2026-08-20)
    Two distinct regimes in the Geneva REn: the IDC (art. 14) applies to owners of heated buildings; individual heating-cost accounting (art. 14B) applies from 5 off-takers.
  10. République et canton de Genève (OCEN) — Que faire selon le résultat IDC de votre immeuble (accessed 2026-08-20)
    Confirmed by the OCEN: above 125 kWh/m²·an (450 MJ/m²·an), an energy audit and optimisation measures are required (REn art. 14; LEn art. 15C).
  11. République et canton de Genève — Règlement d'application de la loi sur l'énergie (REn), rsGE L 2 30.01, art. 14 et 14B (accessed 2026-08-20)
    Geneva REn, art. 14: significant exceedance set at 800 MJ/m²·an until 31.12.2026, 650 MJ/m²·an from 01.01.2027 to 31.12.2030, 550 MJ/m²·an from 01.01.2031.
  12. République et canton de Genève — Règlement d'application de la loi sur l'énergie (REn), rsGE L 2 30.01, art. 14 et 14B (accessed 2026-08-20)
    Geneva REn, art. 14: works ordered after a significant exceedance must be carried out within 36 months; improvement measures after a simple exceedance within 12 months.
  13. Passivhaus Institut, Darmstadt — Criteria for the Passive House, EnerPHit and PHI Low Energy Building Standards (2022 · accessed 2026-08-20)
    PHI criteria: EnerPHit compliance is shown either by the component method (table 2) or by the energy demand method (table 3) — only one of the two need be met.
  14. Minergie Suisse — Règlement des labels MINERGIE®/MINERGIE-P®/MINERGIE-A®, version 2026.1 (2026 · accessed 2026-08-20)
    Minergie regulation 2026.1, sec. 6.1: retrofit ≤ 90 % of the Qh,li MoPEC 2025 limit values per SIA 380/1:2016; ≤ 70 % for new build.
  15. Minergie Suisse — Règlement des labels MINERGIE®/MINERGIE-P®/MINERGIE-A®, version 2026.1 (2026 · accessed 2026-08-20)
    Checked against Minergie regulation 2026.1: Minergie-P covers new build and retrofit under a single procedure; neither module certification nor a dedicated procedure for protected buildings appears in it.
  16. Minergie Suisse — Règlement des labels MINERGIE®/MINERGIE-P®/MINERGIE-A®, version 2026.1 (2026 · accessed 2026-08-20)
    No Minergie document sets an absolute "≤ 30" value: regulation 2026.1 expresses retrofit as a % of MoPEC 2025 (≤ 90 %), with a 15 kWh/m²·an floor.
  17. Passivhaus Institut, Darmstadt — Criteria for the Passive House, EnerPHit and PHI Low Energy Building Standards (2022 · accessed 2026-08-20)
    The PHI criteria mention no maximum time limit: the EnerPHit Retrofit Plan allows pre-certification, then a certificate application after the final step.
  18. Minergie Suisse — Règlement des labels MINERGIE®/MINERGIE-P®/MINERGIE-A®, version 2026.1 (2026 · accessed 2026-08-20)
    Edition in force for air permeability measurement: ISO 9972:2015, complemented by SIA 180:2014 for Swiss application.
  19. Minergie Suisse — Règlement des labels MINERGIE®/MINERGIE-P®/MINERGIE-A®, version 2026.1 (2026 · accessed 2026-08-20)
    Minergie regulation 2026.1, sec. 8.1: fossil fuels not allowed for heat generation, with narrow exceptions (peak load ≤ 10 % above 80 kW; district heating ≤ 50 % fossil).
  20. GEnergie / canton de Genève — HPE — Rénovation variante CECB®, mesure M-13 (accessed 2026-08-20)
    GEnergie rate, measure M-13 "HPE retrofit, CECB® variant": 390 CHF/m² for single-family housing, 210 CHF/m² collective, 150 CHF/m² other uses. Revised annually.
  21. République et canton de Genève — Subventions énergétiques 2026 : 80 millions de francs pour accélérer la rénovation du parc bâti genevois (2026-02-02 · accessed 2026-08-20)
    Canton of Geneva announcement of 2 February 2026: CHF 80 million in energy subsidies for 2026, CHF 10 million more than in 2025.

A retrofit project — or an IDC to bring back into line?

Envelope strategy and critical review of the file — let's talk about your building and its timeline.

Get in touch